Question List

Question1: You are the program manager for your organization and are coaching Bonnie, a project manager, who would like to be a program manager wants to know what a program is. Which one of the following statements best defines what a program is for Bonnie?

Question2: You are the program manager for your organization. You are examining the order of the activities in your program schedule and would like to change some of the ordering to alleviate scheduling conflicts, risks, and based on your experience with the discipline the program uses. Some of the activities you can rearrange while some of the activities must be completed in a particular order. What term describes the activities that can happen in any order?

Question3: You are the program manager of the NHQ Program. The program has reached its final deliverable and the certificate of completion has been created for the program. What else should you, the program manager, create at this time?

Question4: Which of the following documents sets the project objectives?

Question5: What quality control chart compares two or more variables over time to determine how closely the variables may be related to one another?

Question6: You are the program manager for your organization and are working with your team to create the program scope management plan. This plan defines several things in your program except for which one of the following?

Question7: Which of the following is not a template element that is designed to make the project more effective?

Question8: Part of your job as the program manager is to coach the project managers on their duties and goals. One of the project managers, Holly, is having trouble discerning the difference between quality assurance and quality control. She understands that she needs both to help you reach the program goals. Which statement best describes quality control for a project within your program?

Question9: Communication is large percentage of program execution as the program manager must communicate with the appropriate stakeholders. In larger programs face-to-face communication is not always possible.
When emails are used what verbal aspect of communication is lost?

Question10: You are the program manager for the HNY Corporation and you complete programs for other companies in your role. You have just been assigned a new program that is very similar to a recently completed program you did for your company. Management has asked you to create a cost estimate for the program so you base your current cost estimate on the recently finished program. What type of estimating technique have you used in this instance?

Question11: There are five stages of team development. At which stage are there likely to be disagreements and struggle for roles in the program team?

Question12: Olive is the program manager for her organization. She has created a request for proposal for a large portion of her program. In this work to be procured she has set several requirements for the vendors to participate. The chief among these requirements is a vendor must have at least four licensed electricians in his team. This requirement for four licensed electricians is an example of which one of the following terms?

Question13: You are the program manager of the NHQ Program. You will need to initiate six projects for your program.
When should project initiating happen within a program?

Question14: You are the program manager for your organization and you are trying to determine the possible outcomes of a risk event. You're analyzing the risk event's worst case scenario, most likely scenario, and optimistic scenario to simulate the possible affects of the risk on the program's cost, time, and scope ramifications.
What simulation technique are you using in this situation?

Question15: Management is trying to determine which program to initiate. Each of the potential programs has the possibility of creating an income for each it is in existence. Management would like to consider the present value for each year a program creates a return on investment. What program selection method is management using in this instance?

Question16: You are the program manager for your organization and are working with Tracy, one of the project managers in your program. Tracy is having some trouble understanding the concept of the critical path in her project's network diagram. Which one of the following is the best definition of the critical path?

Question17: A knowledge area defines a subset of program management and its processes within that domain. For example, the knowledge area of quality management includes the processes related directly to quality management only. Which knowledge area ensures that all knowledge areas interact correctly with one another?

Question18: Tom is program manager for his organization. His program is scheduled to last ten months and has a cost estimate for the program of $550,000. It is now month nine and Tom reports that he actually has a cost variance of a positive $56,000. While Tom is pleased, the new management is not. Why is a positive cost variance not necessarily good news?

Question19: Your program has a budget at completion of $1,550,000 and is expected to last one year.
Currently your program is 45 percent complete and has spent $725,000. According to the program schedule you are actually to be fifty percent complete at this, but due to some vendor delays your program is running just a bit late. Management is concerned that your program will not be able to recoup the costs of the expenses. They've asked you to determine the cost variance for the program. What is the cost variance based on this information?

Question20: Terri is the program manager for her organization and she's working with Alice, a project manager in her program. Alice calls Terri and insists that she add a change to program scope. Terri agrees that the change should be entertained. What must Alice do to move forward with her change request?

Question21: Julie is the program manager of the NHQ Program for her organization and she believes the program is now complete. Julie is closing her program, and she's working with her program sponsor to review the program's deliverables and benefits. Janet, the program sponsor, is very pleased with the program and agrees that the program has met the program scope. What should Julie and the program sponsor do next?

Question22: Rick is a Program Manager for a large construction program. The program contains four projects.
Stakeholders have requested for some changes that will change the scope of the program. Rick needs to monitor and control program scope. He is required to analyze the change request with detailed deliverables, acceptance criterion, and the work of the program. Which of the following documents will help him for this?

Question23: You are the program manager for your organization and working to create the program statement of work for approval by the program director. All of the following information is defined in the program statement of work except for which one?

Question24: You have created a control chart for a repeatable process in your program. You have discovered that the seven most recent measurements are all on the positive side of the mean in your control chart. What is this phenomenon called?

Question25: Which of the following is described in the statement given below?
"It serves as the primary input for the Plan Program Stakeholder Management process, as well as for the distribution of program reports and other communication."

Question26: You are the program manager for your organization. Management has asked that you determine when resources, such as leased equipment, are no longer needed so that you may release the resources to save time, money, and utilization of resources within your program. What program management process is management asking you to perform?

Question27: Your program has been selected and its program charter is now being created. The program charter defines all of the following characteristics except for which one?

Question28: You are the program manager for your organization and you're coaching Tom, an aspiring program manager, on program management. Tom is curious about controlling communications. Which one of the following is an output of the communications control process?

Question29: You are the program manager for the NHQ Program. Your program has a budget of
$4,500,000 and has lasted for two years. Your program has just completed its final deliverable and you're completing the final program closure processes. What document must the program customer must now sign as part of program closure?

Question30: You are the program manager for your organization and your team has reported on a new issue among your program stakeholders. You want to address this issue as soon as possible, but it will need to be studied and reviewed. You recommend that Shirley, one of your program team members, study the issue and present a few solutions in a week's time. What else should you do with the issue?

Question31: Which one of the following is not considered one of the three components of the Iron Triangle?

Question32: Your program will create new software and install new hardware for your organization. Some of the goals of the program is to improve employee morale, improve customer service, and boost customer satisfaction.
These intangible goals need metrics. What program stakeholder is responsible for quantifying these goals?

Question33: You are the program manager for the JQN Program in your organization. There have been some delays in your schedule and you're about to perform some schedule control activities. Which one of the following will not help you as you perform schedule control?

Question34: At what point in the project is the risk of failing to achieve the project objectives the greatest?

Question35: You are the program manage of HYH Program for your organization. Your program is to create a new sports arena for your city within 12 months. Your program has seven projects and you've worked with all of the project managers before. Even though you've worked with the project managers before you still need to define the authority of the project managers and their projects. What document names the project manager for the project?

Question36: You are the program manager for your organization. Your current program is to create a new recreational facility in your city. Franklin, the Chief Executive Officer, is concerned about meeting all of the financial and schedule requirements of the proposed program. Martina, the mayor of your town, wants to make certain the program meets all safety requirements and building codes. Your supervisor, Mary Ann, is the Program Director, and she is concerned about the start date of your program. Another stakeholder, Hal, is worried that your resources may be spread thin on the program as some of the resources are on multiple projects in your program. To whom will you report to in this program?

Question37: You are the program manager for your program and are creating a communications management plan.
Management wants you to address the type of communications based on the number of communication channels you'll have within the program. Currently there are 345 stakeholders in your program but next week you'll have 387 stakeholders. How many more communication channels will you have next week in your program?

Question38: You are the program manager of the NHQ Program. You are working with your program team to ensure that the work in the program is done accurately and according to scope. You are also reviewing the team inspection process that will need to be done to ensure that the work is being done according to the scope.
If the work is found to be defective it will need to be corrected before the program customers can inspect the work. What process are you completing to ensure that the work is done accordingly to scope?

Question39: You are the program manager for your organization. You're currently creating an accountability matrix starting with yourself, the program manager and the program sponsor. What program management process identifies the program sponsor?

Question40: Your company and a competing company have created a teaming agreement for an opportunity. Through this team agreement you and your competitor can complete a major program for a client. This is, technically, a risk response for both organizations. What type of risk response are you dealing with in this instance?

Question41: You are the program manager of the HNG Program. This program has a budget at completion of
$2,345,900 and is expected to last two years. The program is currently 30 percent complete and you have spent $789,000. The program is supposed to be 35 percent complete but do to some delays you're slightly behind schedule. Based on this information, what is the schedule variance (SV) of this program?

Question42: You are the program manager for your organization. A new program is about to initiated and Marcy, your assistant, asks you about the themes that all new programs must map to. All of the following are themes that you can discuss with Marcy except for which one is not a program theme?

Question43: You are the program manager for your organization. You and your program team have been creating and transferring the program benefits to operations as feasible in your program execution. The process of delivering the program's benefits describes what process in program management?

Question44: If a risk has a probability of 60 percent and an impact of -$57,000 what will the expected monetary value of the risk event be?

Question45: Kelly's program is slipping on its schedule. Management is worried that the program will be late and this will cost the organization several thousand dollars in fines and penalties. They've asked Kelly to use a schedule duration compression technique that will help the program finish on time. The technique that Kelly can use, however, should not add costs to the program. What duration compression technique should Kelly use in this instance?

Question46: Which of the following is used to build consensus through rounds of anonymous surveys?

Question47: Joan is the program manager for her organization. Management has asked her to create a centralized reporting system to capture information on program work, risks, changes, benefits management, and other aspects of the program. What solution can Joan implement to capture, communicate, and record the information management wants?

Question48: Which of the following documents contain a list of all problems, unfavorable events, or situations that occurred so far in the program?

Question49: You are a program manager for your organization. You have proposed a program to the management that will last four years and will cost $35 million to create. Management has asked to see the program charter and the proposed costs and benefits of the program.
Management agrees to your program charter and proposed to fund the program in increments at the completion of each milestone. What type of funding does management proposed for this program?

Question50: A project manager in your program has estimated the cost of a program to be $145,000. As the project manager's project comes close to completion, the project manager realizes that he has still $27,876 left in his project budget. He decides to add some additional features to the project's deliverables in an effort to use the remaining budget. These additions will add value to the project and the project customer is likely to enjoy these new features. This is an example of what term?

Question51: You are the program manager for your organization. As your program is being initiated there is some initial concern from the management about the utilization of resources in your program and the need for resources in their day-to-day roles in operations. Management has set a limit on your program that resources may only work 20 hours per week on the program. What is this limit of resource hours in a time period known as?

Question52: Which of the following types of floats are available? Each correct answer represents a complete solution.
Choose two.

Question53: In which of the following processes is the program charter created?

Question54: Part of your job as the program manager is to coach the project managers on their duties and goals. One of the project managers, Holly, is having trouble discerning the difference between quality assurance and quality control. She understands that she needs both to help you reach the program goals. Which statement best describes quality assurance for a project within your program?

Question55: You are the program manager for your organization. Your program has recently completed its program scope and you've transferred the benefits to the operations of your organization. Before your program is considered closed you must complete some forms and procedures as required by your organization. The requirements to complete the forms and paperwork are also known as what?

Question56: Joan is the program manager for her organization. Throughout the program life cycle there will be several elements, resources, and benefits that can be transitioned from her program to the organization. What document defines how these things can be transferred from the program to the organization?

Question57: You are the program manager of the GHY Program. Your program team has identified a risk dealing with the materials you will be using in the program. It is possible that if the materials are not installed properly they will cause serious damage in future phases of the program. Your team has recommended additional training and a consultant to help the team members install the material accurately to reduce the likelihood of the risk event. You agree and the team executes the risk response. What type of risk response have you implemented in this situation?

Question58: Which of the following information gathering techniques is described in the statement below?
"Project risk experts participate in this technique anonymously. A facilitator uses a Questionnaires to solicit ideas about the important project risks. The responses are summarized are then recirculated to the experts for further comment."

Question59: You are the program manager of the MQQ Program. Your program will use equipment and materials that are new to your industry. You have some concerns that there will be delays and waste by your program team because they've not worked with these materials or tools before. You elect to send the resources that will work the most with these tools through training. The cost of the training in this instance is known as which one of the following?

Question60: You are the program manager for your organization. Your program has a budget of $750,000 and is expected to last one year. The program is currently 30 percent complete and has spent $245,000. The program is supposed to be 40 percent at this time. What is the schedule performance index (SPI) for this program?

Question61: Which of the following individual should respond to the risk with the preplanned risk response?

Question62: Andy is the program manager of the HQN Program. This program is nearing its completion and there is still
$25,000 left in the program budget. Andy has asked the program team to identify some extra deliverables that can be included in the program scope to improve the program deliverable but also to use all of the funds in the budget. What term is assigned to the actions that Andy is trying to do in this instance?

Question63: Which one of the following is not an output of the direct and manage program execution process?

Question64: During the selection of source process, you assign certain points towards various categories to judge the vendors. Which type of source selection process is it?

Question65: You are the program manager for your organization and you're dealing with several issues about the materials used in the program. Right now, the issues have been assigned to issue owners for resolution in ten days. In the interim, what should you do with the issues?

Question66: A new program is being initiated for the HNQ Organization. The program manager is working with the business analyst and management to define several attributes of the program. All of the following are identified during program initiation except for which one?

Question67: Josh is the program manager for his organization and he's leading the analysis for a new program that may be initiated by his company. The analysis is a focus on the return on investment for new software that may be created if the program is initiated. What type of a document is Josh likely creating for his company?

Question68: Which of the following statements are true regarding program scope changes?

Question69: Which of the following represents the duration of activities against a calendar?

Question70: What is the formula to determine earned value (EV) for a program?

Question71: What project management term would you associated with a predetermined budget you're your program?

Question72: What does RACI stand for?

Question73: Your program is to construct a new condo building in Chicago. You and the project managers are working together to define the project assumptions about the program. Which one of the following is an example of an assumption for this program?

Question74: Which one of the following is NOT a component of the risk monitoring and controlling process?

Question75: You are the program manager for your organization and are about to execute your procurement management plan. You need to procure materials for your program and you want only the vendor to provide you with a price for the goods you need to procure. What type of a document should you provide to the vendor in this scenario?

Question76: When is the lessons learned document updated?

Question77: You are the program manager for your organization. Your program team has 43 people that all need to be monitored and controlled. You would like to create a standardized report that you can use to monitor, control, and record the performance of each staff member in your program. What type of report can you create that will help you track your staff and their performance?

Question78: Which project management meeting allows stakeholders to meet one another and to learn about the project?

Question79: Which of the following program process outputs includes causes of variances from the program management plan, corrective actions taken and their outcomes, risk mitigations, and other information of value to management and stakeholders of future programs?

Question80: Which one of the following is the best example of transference?

Question81: Holly is the program manager for her program. She is creating with her team a plan that will address how the program team will achieve program goals based on who the program will need to interact with in the program. This plan should define all of the people, groups, and other entities the program needs to interact with in order to move the program forward. On what plan is Holly working?

Question82: Which of the following terms is used for a schedule compression technique where two activities that were previously scheduled to start sequentially start at the same time?

Question83: You are the program manager for your organization. Management is considering a new program but they are worried about the program risks that may affect the program success. You know that there are three positive risks responses and three negative risk responses that each risk can have. Management asks you which risk response would be most appropriate for a large risk event if they wanted to hire a third-party to own the risk event for the program. What risk event is most appropriate?

Question84: Leigh is working with the project stakeholders to define the project scope. The stakeholders are deciding on what type of flooring their new hotel should have in the lobby. They have narrowed their choices to either carpet or tile. The two acceptable choices of carpet or tile during scope definition is an example of what planning approach?

Question85: A program has a BAC of $1,750,000 and is expected to last two years. The program is currently at the third milestone which represents 35 percent of the program work. As it happens, this program has already spent
$620,000 of the budget. Management is concerned that the program may also be slipping on schedule because the program should be forty percent complete by this time. Based on this information which type of performing is present in this scenario?

Question86: There are 1,500 doors to be installed in Tom's program. Each of the 1,500 doors is required by the building code to swing into the room rather than swing out into the hallways. It has come to Tom's attention that part of the team installing the doors has installed nearly 200 doors to swing into the hallway rather than into the rooms. Tom instructs the team to fix the problem. What type of action has Tom taken in this instance?

Question87: Molly is the program manager for her organization. She is creating a document that defines the benefits the program will create for her organization once the program has been completed. What document is Molly writing?

Question88: You are the program manager for your company and evaluating the sellers to determine the seller to buy from. In your analysis you've created a histogram to display the pros and cons for each seller. You've created five categories of interest and assigned values to each category for each vendor. Your five categories are:
Cost

Schedule

Experience

Certification

Warranty

Each category has a different point value and the vendor that receives the maximum points in total will win the contract. What type of seller evaluation are you performing?

Question89: You are program manager for the HYH Program. Your program governance is requiring you to use earned value management to predict how closely your program is tracking to the cost and schedule baselines and to predict overall program performance. Which earned value management formula can you use to predict how much more will need to be invested in the program based on current program performance?

Question90: Who prepares the statement of work (SOW) for external projects?

Question91: Mary has just completed a large program for her organization. What should Mary now do with the program records that she has created throughout the program?

Question92: What is another term that can be assigned to the pre-program analysis and research to determine if a program should be initiated?

Question93: When a change enters your program requirements you must update all of the following documents except for which one?

Question94: You are hosting a meeting with all of the vendors that have received a copy of your statement of work. In this meeting, you'll be discussing the statement of work, clarifying the details, and answering any questions the vendors may have about the project. What is this meeting called?

Question95: You are trying to determine if you should buy or build a solution for your program. If you build the solution it'll cost you $45,000 to create and $7,000 per month to support. A vendor reports that they can create the solution for you for $1,000 but you'll have to pay them $9,000 per month to support the solution. Should you buy or build this solution?

Question96: You are the program manager of the NHQ Program for your organization. Your program has 14 constituent projects that are all creating benefits and deliverables for your program. You have recently terminated the GHW Project in your program because you've made trade-offs with other program projects and the deliverables of the GHW Project are no longer affordable. What project management activity should happen in the GHW Project?

Question97: You are the program manager for your organization and are planning the roles and responsibilities in your program. You would like to create a RACI chart for the program work. What does RACI mean?

Question98: You are the program manager of the NQA Program. In this program you're planning which contract types you'll allow into the program and which ones you will not. One contract type you won't accept is the cost plus percentage of cost contract. Which of the following is a valid reason you would not allow this contract type into your program?

Question99: You are the program manager of the GHY Program in your organization. It has come to your attention that some of the project managers in your program are adding time to each project activity in an effort to pad their durations in case some event happens in their project that will cause delays. What principle should you share with these project managers that counterattack the concept of padding activities with additional time?

Question100: You have completed a project for a client at his facility. The project has lasted for 18 months and you have generated many reports, plans, change request forms, and other documents about the project work. What should you do with the project documentation?

Question101: Small changes that bypass the organization's change control procedures are called ____.

Question102: You are the program manager for the SRQ Program. You have rejected several change requests for the program scope. What must you do with the rejected change requests?

Question103: Wan is the program manager for his organization. He has been hearing reports that some project team members are complaining about the number of hours they're required to work on the program's projects and that some scheduling of team assignments are conflicting with their regular operational duties. You investigate the problem and agree that many team members are being assigned too much work within a given time period. You decide to enforce resource leveling heuristics to thirty hours of project work per week maximum. What will likely happen to the program and projects?

Question104: Martha is sharing her experience of her last project as the project manager. She tells that when she presented customer a formal acceptance and sign-off document, they refused to sign, claiming that the product does not meet their expectation. Taking which of the following steps could have been prevented the situation? Each correct answer represents a complete solution. Choose all that apply.

Question105: You are the program manager for your organization. You're currently working with the program director, Nancy Holmes, to define a new program and the benefits the program should create. Of the following, which is the best definition of a benefit a program creates?

Question106: You are the program manager for your organization and are coaching your project managers on the program's schedule. Alice wants to know what the schedule control process creates. All of the following are outputs of the schedule control process except for which one?

Question107: Which of the following shows the ratio between a task's budgeted and actual costs?

Question108: Which of the following can be used to help you or other project managers on future projects?

Question109: You are the project manager for the GGG Project and are about to close the project kick off meeting. All of the project team members and the key stakeholders are in attendance. What final item should you talk about before closing the meeting?

Question110: Which of the following is responsible to sign off on the closure documents of a project?

Question111: You are the program manager for your organization. One of the projects within your program is to install
15,000 light fixtures throughout your organization's corporate campus. The new fixtures will save on electrical costs. Which one of the following choices is an ideal approach to quality assurance and the installation of the light fixtures for this project team?

Question112: What document asks the seller to provide your project with a detailed description of a project solution along with a price to complete the project work?

Question113: Which benefit measurement method considers the value of each time period's return for a project that will create deliverables over multiple time periods?

Question114: What cost estimating approach uses the work breakdown structure to create a cost estimate?

Question115: Performing quality assurance in a program can result in which one of the following?

Question116: What percentage of communication is nonverbal?

Question117: You are the project manager for your organization and are working with the project stakeholders and the business analyst to define all of the deliverables the project is to create. The stakeholders would like the option of adding more deliverables later in the project and keeping the requirements somewhat open for changes. You explain to the business analyst that you need a set of requirements that define exactly what needs to be delivered for the project. What document are you trying to create in this early stage of the project?

Question118: Which of the following documents is described in the statement below?
"It is a type of procurement document used to request proposals from prospective sellers of products or services."

Question119: What duration compression technique typically adds risk when it's used during a program?

Question120: Donna is the project manager for her organization. She is preparing a plan to manage changes to the project should changes be requested. Her change management plan defines the process for documenting, tracking, and determining if the changes should be approved or declined. What system is considered the parent of the change control system documented in Donna's plan?

Question121: A program has a budget at completion of $1,250,000 and has already spent $425,000. The program is running late due to some vendor delays; the program is only 30 percent complete though it was scheduled to be 45 percent at this time. Based on this information how much more money will this program need to finish?

Question122: Program management has several themes that the program manager must be aware of.
Which one of the following is not a program management theme?

Question123: Which of the following plans should a project manager implement if a selected risk strategy fails to be fully effective?

Question124: Who owns the program?

Question125: You are the program manager for your organization. You are planning a new program that will construct a new warehouse facility for your company. As you look forward to the conclusion of the program you need an official document that will signify the program has ended. What document should you specify in your program management plan for the conclusion of the program?

Question126: A project manager in your program is using progress elaboration as part of their planning approach. This approach is also known as what planning methodology?

Question127: On which of the following documents you work throughout the risk management processes?

Question128: You are the program manager for the GHT Program for your company. This program has a budget at completion of $789,000 and is currently 40 percent complete, though it was scheduled to be 50 percent at this time. Your program has spent $325,000 of the budget to date. Based on this information, how many pennies is your program losing per dollar spent on the work?

Question129: You are a program manager for a large construction program. You need to ensure that the projects in the program are in accordance with the schedule. You are tracking start and finish dates for them. Which of the following processes are you on?

Question130: Alice is the project manager of the NHQ Project and is entering the project's closing processes. The project, she has managed, has been for another organization in a contractual relationship. Her organization requires Alice to complete performance reviews of the project team, review the deliverables with the project customer, and to obtain formal signoff of the project deliverables. There may be other conditions and activities that Alice likely will need to do in this final project phase. Where can Alice check regarding this project?

Question131: Robert is the program manager for his organization which operates in a matrix structure.
Resources in Robert's program will be utilized on several projects in and out of his program. He wants to be certain that all of the resources will be planned accordingly and that the project managers communicate with one another about when the resources will be needed and utilized in the projects. What plan should Robert create along with the project managers to ensure that the resources are scheduled and managed effectively?

Question132: A team member has made a mistake during the installation of a fixture in your program. You have requested that the team member should correct the problem so that the fixture is installed properly. Once the team members has corrected the problem what action should be taken next?

Question133: You need to create a document that will define the costs, resources, and characteristics of each deliverable the program will create. What document should you create?

Question134: Which of the following risk response planning techniques is associated with threats and seeks to reduce the probability of occurrence, or impact of risk below an acceptable threshold?

Question135: Which of the following contract types is described in the statement below?
"The seller is reimbursed for all allowable costs for performing the contract work, and receives a fixed payment calculated as a percentage for the initial estimated project costs."

Question136: You are the program manager for your organization. Management has asked you to create a method to track the program stakeholders' concerns, threats, and demands for communication. They would like you to map out each stakeholder or stakeholder group and identify trends within the chart to help your program communicate better. What type of a chart should you create for management?

Question137: You are the program manager for the HQM Program. Your program has sixteen constituent projects around the world. You are requiring that each project manager and project management team use the same forms, software, and templates to create standardization in each project. What term is assigned to the forms, templates, and software that your program will provide for your projects?

Question138: You are the program manager for your project. You are working with the project managers regarding the procurement processes for their projects. You have ruled out one particular contract type because it is considered too risky for the program. Which one of the following contract types is usually considered to be the most dangerous for the buyer?

Question139: You are the program manager for your organization. Your current program has fourteen projects and one project manager in your program is about to close her project. She will need all of the following inputs to the close project process except for which one?

Question140: An organization supports both programs and projects for various industries. What is a portfolio?

Question141: You are the program manager for your organization. This program will last for two years and has eight projects. The cost of your program is $4 million and there are some risk concerns that may affect the overall cost of the program. Management is concerned with how long it will take the program to reach the management horizon. What is management horizon also known as?

Question142: What component of the change management system is responsible for evaluating, testing, and documenting changes created to the project scope?

Question143: Hans is the program manager for his organization. His current project has seven constituent projects that each will create deliverables for the organization. Who is responsible for the project deliverables in this scenario?

Question144: Wanda is the program manager for her organization. Her program team consists of resources from across the organization - many of whom have not worked together before. Wanda thinks that she'll need to complete some team development but would like to focus the development on the materials and activities that the program team will need to complete in the program. What plan should Wanda reference and update to complete her team development process?

Question145: The ____ quality assurance technique ensures continuous improvement of all processes.

Question146: A risk response in a project in your program has actually caused new risks. What term is assigned to the new risks that a risk response has created?

Question147: You are the program manager for your organization and you need to define all of the program resources you'll need for your program. All of the following can be considered a program resource except for which one?

Question148: In your program you must adhere to Six Sigma as part of your organization's enterprise environmental factors. There is terminology, reports, and measurements that you are expected to use as part of your program. Six Sigma is an example of what program management process?

Question149: You are the program manager for your organization and are working on gathering the requirements for a new solution and mission statement. There are several instances in the stakeholder pool where the stakeholders and their manager are being queried on possible requirements. You worry that the subordinates may have requirements, ideas, and suggestions to offer but they may be not submitting their thoughts because they do not want to contradict their managers. You believe you need a method to gather all requirements without the stakeholders having any fear of retribution. Which one of the following allows you to anonymously gather iterations requirements and still allow for all stakeholders to review what has been submitted in an attempt to find consensus?

Question150: You are the program manager for your organization and are working with your team to identify stakeholders in the program. Where should the identified stakeholders and their information be recorded?

Question151: You are the program manager for your organization and management has asked you to be certain to finalize the lessons learned documentation for your program. When will the lessons learned documentation be created?

Question152: Your program exists within a matrix structure. Your program has eight projects that all share resources from around the organization. You are concerned that some of the project team members may be over allocated and want to create a chart that will reflect the utilization of resources. What kind of chart can show the utilization of project team members used in your program?

Question153: You are the program manager for your organization. Management has asked you to create a document that will capture the stakeholders concerns, perceived threats, and specific objectives about the program and its projects. What document is management asking you to create in this instance?

Question154: You are the program manager for your organization. Management has assigned you to a new program that has been chartered. Your team is in the process of the Manage Program Issues process. One of the two outputs of this process is change requests. Which one of the following is the other one?

Question155: Complete the following phrase about quality management:
Quality is ____ into a program, not ____ into a program.

Question156: Julie is the project manager of the NHQ Project. She and her project team have successfully finished the project and the customers have signed the project closure agreement. Julie has compiled all of the project records and the project's lessons learned documentation. What should Julie do with the project's lessons learned documentation?

Question157: What is a stakeholder analysis chart?

Question158: Which of the following statements are true regarding the Monitoring and Controlling Program Risks process? Each correct answer represents a complete solution. Choose all that apply.

Question159: All of the following are benefits of a program except for which one?

Question160: You are the program manager of the HNG Program. This program has a budget at completion of
$2,345,900 and is expected to last two years. The program is currently 30 percent complete and you have spent $789,000. The program is supposed to be 35 percent complete but do to some delays you're slightly behind schedule. Based on this information, how many pennies is the program losing per dollar invested in the program work?

Question161: Ben is the program manager for his organization. He's working with program team to determine what activities need to be completed in order to move the program into execution. He and the team are subdividing the program scope into smaller, manageable components to determine the activity list. What is Ben and his program team creating by subdividing the program scope in this scenario?

Question162: You are the program manager of the YHT Program. You have been working with a vendor in the program but have decided that the contract between your program and the vendor needs to be terminated. What two things must be documented if you wish to terminate a vendor's contract?

Question163: As a program manager you must also understand the project management lifecycle and the project lifecycle. What is the difference between the two?

Question164: You are the program manager for your organization that utilizes vendors from several different organizations. A vendor has submitted an invoice for the work they have completed in your program. You have reviewed the work results and agree with the vendor that their contractual obligation is complete.
What should you do next in regard to the vendor's invoice?

Question165: Tom is the program manager for his organization. He has to balance the resources he'll be using in the program with the demand for operations to use the same resources. What program document can Tom reference to determine the availability of certain program resources, such as application developers, engineers, and technical writers?

Question166: Mary Anne is the program manager for her organization. In her program there are six projects. One of the projects in her program has been performing well. It is on schedule and has no cost or schedule variances.
Mary Anne has decided, however, that her program needs to be terminated. Which one of the following is a likely reason why the project should be terminated?

Question167: You are the program manager for your organization and are working with your program team to create the program scope. Based on the program requirements you have identified the major deliverables of each phase in your program scope. Management has requested that you plan for cost estimating to happen at each phase of the program before continuing the work. Management may elect to cancel the program at the end of each phase based on past performance of the program. What are the reviews of management called at each phase?

Question168: You are the program manager for your organization. Your program has a budget of $750,000 and is expected to last one year. The program is currently 30 percent complete and has spent $245,000. The program is supposed to be 40 percent at this time. What is the cost performance index for this program?

Question169: Over the life of your program you've received many change request forms. Some of the change requests have been approved and some have been declined. Where should you record all change requests and their status?

Question170: You are the program manager for a construction program. In this program you are requiring that all workers adhere to the identified safety requirements. Some of the work in the program you've decided is too risky for the program team members so you've hired specialists to manage the dangerous work. The outsourcing of the dangerous work to a specialist is what type of risk response?

Question171: Gary is the program manager for his organization. His current program has 432 stakeholders, some of which are external to his organization. He would like to create a chart that identifies each stakeholder's opinion of the program, influence over program decisions, their requirements and affect on program priorities, and other information. What kind of chart should Gary create in this instance?

Question172: You are the program manager for your organization. Your current program, which has just been initiated, needs to launch several projects in order to create all of the benefits of the program. What document do you need to create in order to initiate the projects within your program?

Question173: Hal is the program manager for his organization. He would like your organization to provide his program with 4 tons of pea gravel for a construction project in his program. Hal send you a statement of work and an IFB. What document should you provide to Hal?

Question174: Don is the project manager of the NQP Project for his organization. This project is scheduled to last for 18 months and will have several elements of the project that have government regulations. Management is concerned with the regulations and would like Don to report on the activities that will be affected by the regulations. What document should Don reference for information on the activities and the regulations?

Question175: Which of the following tools/techniques keep program managers and executives informed of the program's progress?

Question176: Two project managers in your program, Marcy and Mary, are not agreeing with the scheduling of project resources and they have asked for your help to determine the resolution. They are refusing to speak with each other and each is telling you that the other person is scheduling project resources for the project that are already scheduled to complete the work. In the communication model, what component represents the disagreement of these two project managers and their refusal to speak with each other about a resolution?

Question177: Paul is the program manager for his company. He along with his team is working on the Monitor and Control Program Changes process. The process will need several inputs. Which one of the following items is NOT an input to the Monitor and Control Program Changes process in the program management?

Question178: You are the program manager for your company and management wants you to identify how you'll make decisions in the program planning processes. What program management document should serve as the baseline for all future program decisions?

Question179: Which earned value management formula can help you determine how likely it is that you'll complete the program based on the amount of cash left in the program budget?

Question180: In your organization there are rules and procedures that the program manager must follow and abide by before the program can begin and must continue to follow once the program is in execution. What term is assigned to the enforcement of these program management rules and procedures?

Question181: Your program has just been chartered during the program initiation process. Your program also needs to create three program statements. Which program statement defines how your program will manage tradeoffs, competing objectives, and program and organization decisions?

Question182: You are the program manager for your organization. You have created a statement of work, request for proposal, and an invitation to a bidder's conference for 17 possible vendors. During the conference there were questions about your request for proposal and statement of work that led to clarifications. After the vendor conference you should update what information to send back to the vendors?

Question183: All of the following are resources that you will need to monitor and control in a program environment except for which one?

Question184: You are working with Sam, a project manager on one of the projects within your program. Sam doesn't understand all of the rules and procedures that he's required to do as a project manager in your program.
What are the rules and procedures called in project that Sam must abide by?

Question185: You are the program manager of the YGH Program. A vendor has recently completed his contracted work for your program. You agree that the vendor has completed the procured work so what document should you and the vendors now sign?

Question186: Which of the following statements is most accurate about the critical path?

Question187: You are identifying stakeholders for your program to create new software for your organization. The software will affect the ordering by the customer, the manufacturing of the product, inventory, and account management. Sarah, a key stakeholder in your program, is skeptical of one application affecting so many parts of the organization. She prefers that several applications be created instead of the approach your program will take. In stakeholder identification how would you categorize Sarah?

Question188: You are the program manager of the OFE Program. You are working with your program team and project managers to ensure that there is consistency in the execution of the program plan. You stress that the work has been planned and now the team must accurately complete the work. You want to ensure that the work is done correctly the first time in the program. What type of process are you stressing to your program team and project managers?

Question189: You are the program manager for your organization. Your program is about to being initiated and management is asking you for a document that will define all of the required resources, skills, and competencies you'll need in your program. What document defines the skills and competencies for a program?

Question190: June is the program manager for her organization. Management has asked June to create a visual mapping of the program scope so that all of the key stakeholders can see all of the elements of the program scope. June needs to create what kind of document to show all of the program deliverables based on the program scope?

Question191: You are the program manager for your organization and are planning the composition of the project team.
In your organization resources are used from throughout the company and may serve on more than one project. While you, the program manager, will have most of the authority on the program you want the project managers to have authority over the project decisions. What type of an organizational structure does your organization have?

Question192: What is the primary purpose of a project kick-off meeting?

Question193: If a program has a budget of completion of $550,000, is 25 percent complete, and has spent $135,000 what is the cost variance (CV)?

Question194: Which of the following tools and techniques are parts of the Administer Program Procurements process?
Each correct answer represents a complete solution. Choose all that apply.

Question195: Which of the following documents describes the details for each component in the WBS?

Question196: Which of the following is NOT true regarding the program work breakdown structure (WBS)?

Question197: You are the program manager for your organization and are reviewing several proposed change requests for your program. Mary, a stakeholder, who has made a change request is asking why it is taking you so long to review the change. You tell her that you must perform integrated change control to review each change request. What is integrated change control?

Question198: You are the program manager for your organization and you are preparing to launch several constituent projects within your program. You need to ensure that each project manager is authorized to utilize the appropriate project and program resources in order to complete the project requirements. What document do you need to create for each constituent project in your program to ensure that each project manager can use the appropriate resources?

Question199: Identify the term described in the statement given below? "The use of it should be reviewed along with an assessment of their effectiveness. This will aid the program management in determining if risks to the program are being effectively managed. It also provides feedback to the program management on any projects that need to be recovered or terminated."

Question200: What should a program manager do when a scope change has been approved that will drastically affect the program costs assuming that the costs will be added to the program budget?

Question201: You are the program manager for your organization and you're trying to determine if you buy or build a software solution for your organization. If you build the solution it'll cost you $75,000 to create and it'll cost you $12,000 per month to support. If you hire a vendor they can build the solution for $63,000 but their solution will cost you $15,500 per month to support. How many months would you have to use your in- house solution to equate to the cost of the vendor's solution?

Question202: You are the program manager for the HGQ Program in your organization. Your program has eight constituent projects including a small project which you've assigned to Beth a new project manager in your organization. Part of your assignment is to coach Beth on project management in your program. You are telling Beth about the five process groups of project management and how they map to the progression of the project. Which process group would you tell Beth is where she'll likely spend the bulk of the project time and the project budget?

Question203: Who makes Go/No-Go decisions during phase gate reviews?

Question204: You are the program manager for the BHN Program. Your program has 122 stakeholders that you'll need to plan to communicate with. Considering the size of the program how many communication channels do you have in this program?

Question205: Mike is the program manager of the NHQ Program. Mike and a vendor are in disagreement over the deliverable the vendor has created for Mike's program. Mike does not believe the vendor has correctly created the deliverable, while the vendor is adamant that his company has indeed completed the contract.
Both parties have documented their stance in the debate.
This is an example of what?

Question206: You are a program manager of a program. You are required to compile performance data of your program.
These data will be sent to relevant stakeholders. You are reviewing the status reports of all projects including the costs, schedule, scope, risks, and other performance datA.
In which of the following processes are you working on?

Question207: You are the program manager for a new software development program. One of the developers has been adding extra fields for information in the software that was not part of the original program scope. While the fields are a good idea, the customer did not ask for the information and some time has been wasted on this work that was not in the program scope. This is an example of which one of the following terms?

Question208: All of the following are resources that need to be monitored and controlled except for which one?

Question209: You are the project manager of a construction project. You have to close a phase of the project. Which is the only technique (or tool) available in the Close Project or Phase process?

Question210: You are the project manager for your organization. Your project team has finished the second phase of a seven-phase project. At the end of each phase, management must review the work your project team has completed and determine if the project should be allowed to continue. What name describes this type of end-of-phase review management is completing on your project?

Question211: An organization is considering a new program. The business analyst believes that the benefits to the organization would equate to $1,550,000 in five years. If the rate of return for this program is six percent what is the maximum amount the organization should invest in this program?

Question212: What does CPI value less than 1.0 indicates?

Question213: You are the program manager for your organization. Part of your role as the program manager is to train John, a new program manager, on the program processes within a program. John is confused as to when the program team can be acquired in the program management lifecycle. When will the program team be acquired for a program?

Question214: You are the program manager for your company and are monitoring and controlling several aspects of your program. You want to make certain that you're including all areas that need to be monitored and controlled. Which one of the following is not something you'll have to monitor and control as a program manager?

Question215: Which one of the following is the best definition of program quality?

Question216: What document should you provide to the vendors if you're only interested for a set fee for their materials?

Question217: Martha is the program manager for her organization. One of the projects of a program is done but is also considerably over budget. Kay, the project manager, has elected to crash the project in order to recoup schedule delays but this increased the project costs. What should Martha instruct Kay to do with the information regarding the schedule delays and cost overruns?

Question218: Robert is the program manager of the NHQ Program. His team has never worked with one another before this program and he is worried about their abilities to become a team in very short order. He would like to create a team development exercise to facilitate this process. Robert will need all of the following information except for which one to facilitate team development?

Question219: You are the program manager for your organization. Your current program, which has just started, has eight projects and many of the projects share resources such as equipment and people. Management has asked that you identify when the project resources will be utilized on each project within your program.
They are worried some resources may be idle or overscheduled. What approach can you use to consider the availability of resources when the project managers begin sequencing their project activities?

Question220: Which of the following directs the improvement efforts to those areas that will have the biggest impact?

Question221: You are the program manager of the HNG Program. This program has a budget at completion of
$2,345,900 and is expected to last two years. The program is currently 30 percent complete and you have spent $789,000. The program is supposed to be 35 percent complete but do to some delays you're slightly behind schedule. Based on this information, what is the schedule performance index (SPI) for this program?

Question222: Which of the following statements are true regarding program scope statement?

Question223: Part of program management is to understand how the communication model works in a program. The program manager must be able to effectively communicate with the program team and stakeholders. What component of the communication model is responsible for carrying the message?

Question224: You are coaching Tammy, a project manager in your program, on the benefits of program management.
She is stumped as to why you would create a program so you're sharing with her all the difference benefits of a program. Which one of the following is a benefit of creating a program?

Question225: After program closure, the lessons learned document becomes the part of ____?

Question226: Part of program management is to identify what motivates your program team members. If you subscribe to Maslow's Hierarchy of Needs which need is at the top of the hierarchy?

Question227: You are a program manager for an environmental program. The program involves installation of windmill across the country. During execution of the project, a stakeholder raises a change request to add an additional module with the existing installation. The program governance board has approved the change request. Which of the following is true regarding this scenario?

Question228: An organization is considering a new program. The program has a cost of $1,950,000 and will last for three years. What is the minimum future value this organization should expect to receive from this program if it is initiated and the rate of return is six percent?

Question229: Which of the following increases when one fast tracks the project?

Question230: Your program creates a byproduct that you could sell to a client. The cost of the byproduct would offset the cost of the program by nearly $7,500 per month. This is an example of which positive risk response?

Question231: You are the project manager for the JJY Project, which is similar to the HHG Project you managed last quarter. You would like to model the current project scope on the previous project to save time and effort.
This is an example of what kind of scope definition?

Question232: What analysis type could you use in a program to compare the positive stakeholders and their position, power, and influence over your program to the same variable components of the negative stakeholders in your program?

Question233: Ned is the program manager for his organization and he's considering some new materials for his program. He and his team have never worked with these materials before and he wants to ask the vendor for some additional information, a demon, and even some samples. What type of a document should Ned send to the vendor?

Question234: You are the program manager for your organization. Your program will create a new condominium in your community. There are several concerns about the condos including the timing, the local economy, the environment, and the proposed schedule. You and your team are creating the program management plan to address these concerns along with identifying the constituent projects that will build the structures and deliverables. What group will need to review your program plan to approve the plan before you may proceed in the work?

Question235: You are the program manager of a new program in your organization. This program will last for one year and your program team will work full-time on the effort. The nature of the work requires that the program team work closely together for the next year, but many of the program team members have never met one another. You decide to take the team on an outing where they can work together through challenges, learn teamwork, and get to know one another. This is an example of what process?

Question236: Gary is program manager for his organization. His current program is over budget and is slipping on the program schedule. Management has demanded a change to the program scope. What is the most likely type of change management would make to this program scope?

Question237: Your program has a budget at completion of $1,550,000 and is expected to last one year.
Currently your program is 45 percent complete and has spent $725,000. According to the program schedule you are actually to be fifty percent complete by this time, but due to some vendor delays your program is running just a bit late. Based on this information which is performing worse, the cost or schedule?

Question238: What is the other name for critical delivery dates?

Question239: Your program has 121 stakeholders that you'll need to communicate with. Your communications management plan defines how the communication should happen, what should be communicated, and the expected modality of the communications. You'll also need which one of the following as an input to the information distribution process in your program?

Question240: Robert's program is slipping on its schedule and management has asked that Robert find a method to compress the duration of the program. What approach could Robert take that would not dramatically add risks to program if he added labor to the effort-driven activities within the program?

Question241: Harriet is the program manager of a large program that has a high profile and visibility in her organization.
Some of the stakeholders are negative and Harriet needs to work with these stakeholders to address their fears, perceived threats, and concerns about the program. Which communication method is considered to be the best approach for this scenario?

Question242: You are the program manager for your organization and you are dealing with your program stakeholders.
You are explaining to them, along with your program team, how certain activities in the program may cause delays in the schedule if the associated risk events come into play. The cost of impact of the risk events are minimal, but the schedule impacts could be bigger. The stakeholders are concerned about delaying the schedule beyond a given due date for the program. They would like you to determine if it is possible to add more labor, use a higher grade of material, or hire some consultants to ensure the risks do not occur in the program. They are not much concerned about the cost of the solution as long as the solution or identified risks do not delay the program completion. What type of risk response are your program stakeholders recommending in this situation?

Question243: You are the program manager for your organization. Management would like to consider the present value for your program. If your program is predicted to be worth $450,000 in two years what is the present value of the program if the interest rate is six percent?

Question244: You are the program manager for your organization. You have created a program that will create things for the organization throughout the program not only at program closure. All of the following are elements that you may transfer to the organization throughout the program's life cycle except for which one?

Question245: You work as a program manager for a large construction program. Your program includes constructing hotels across the country. You collect information on the status of the program. During comparison with the original plan you find the 200 hotels have been completed as against 275 hotels planned as of today. In which program process are you working on?

Question246: You are the program manager of the BHG Program. One of the projects in your program will be using new materials that are somewhat untested. You are worried that there may be delays and waste because the project team is unaware of how to accurately use these materials. You elect to send the people that will be using the new materials through training on how to complete their project work. You also allow them to purchase some of the materials to experiment on their use before the actual project work is to be done.
You want to ensure that mistakes do not enter into the project. What type of action have you provided in this scenario?

Question247: Where are negative risks recorded?

Question248: According to Standard for Program Management, Second Edition, how many knowledge areas are involved for program management?

Question249: What schedule analysis simulation tool allows you, the project manager, to review possible combinations of events such as optimistic, most likely and pessimistic outcomes for your project?

Question250: You are the program manager for your organization and are planning the program. One of the plans you need to create will define how you'll transfer the benefits of the program to the operations of your organization. Which program management plan defines this process?

Question251: You are the program manager of the JNH Program. Tom, a project manager in your program, has just completed his project and is ready to officially close his project. You agree that Tom's project is completed.
What role do you play in Tom's project closure?

Question252: A wild life protection organization opposes your program, which involves the cutting of around 200 trees to make way for the construction of a building. Which of the following correctly defines the organization in program management terminology?

Question253: You are the program manager for a large program in your matrix organization. You need to define when the resources in your program will be brought into the program and then released from the program so that the project managers, operational managers, and your program team can plan accordingly. What program management plan defines when resources are needed, how the resources will be obtained, and how the resources may be released from the program?

Question254: Paula is program manager for her organization. It has come to her attention that several of the projects within her program have stalled which has now caused her project to be delayed. Paula is required by her organization to create a certain type of report when there are variances in the program dealing with time and cost. What type of report is Paula likely to create in this instance?